- February 20, 2025 at 11:39 am
B2Gold financials out today and looks like they want to develop Gramalote. If they do, they will have to deal with Zonte. A bankable feasibility will have to reveal the status of all claims etc.Gramalote Project Development
On June 18, 2024, the Company announced the results of a positive PEA on its 100% owned Gramalote Project located in the Department of Antioquia, Colombia. The PEA outlines a significant production profile of 234,000 ounces of annual gold production for the first five years, with average annual gold production of 185,000 ounces over a 12.5 year project life with a low-cost structure and favorable metallurgical characteristics. Additionally, the PEA outlines strong economics with an after-tax NPV<sub>5%</sub> of $778 million and an after-tax internal rate of return of 20.6%, with a project payback on pre-production capital of 3.1 years at a long-term gold price of $2,000 per ounce.
The pre-production capital cost for the project was estimated to be $807 million (including approximately $93 million for mining equipment and $63 million for contingency). A robust amount of historical drilling and engineering studies have been completed on the Gramalote Project, which significantly de-risks future project development. Based on the positive results from the PEA, B2Gold believes that the Gramalote Project has the potential to become a medium-scale, low-cost open pit gold mine.
B2Gold has commenced feasibility work with the goal of completing a feasibility study by mid-2025. Due to the work completed for previous studies, the work remaining to finalize a feasibility study for the updated medium-scale project is not extensive. The main work programs for the feasibility study include geotechnical and environmental site investigations for the processing plant and waste dump footprints, as well as capital and operating cost estimates. Those work programs, as well as processing engineering and site infrastructure design, are underway and the study is on schedule.
The Gramalote Project will continue to advance resettlement programs, establish coexistence programs for small miners, work on health, safety and environmental projects and continue to work with the government and local communities on social programs.
Due to the desired modifications to the processing plant and infrastructure locations, a Modified Environmental Impact Study is required. B2Gold has commenced work on the modifications to the Environmental Impact Study and expects it to be completed and submitted shortly following the completion of the feasibility study. If the final economics of the feasibility study are positive and B2Gold makes the decision to develop the Gramalote Project as an open pit gold mine, B2Gold would utilize its proven internal mine construction team to build the mine and mill facilities.
Capital expenditures in 2025 at Gramalote are expected to be relatively consistent throughout the year, totaling $28 million related primarily to feasibility study costs and ongoing care and maintenance.